Re: Tetrad Development (Civic Auditorium)
Should see visible demo on the building next week.
Re: Tetrad Development (Civic Auditorium)
Thanks for the info! I'm super excited about the future of this siteiamjacobm wrote:Should see visible demo on the building next week.
-
- Home Owners Association
- Posts: 79
- Joined: Fri Jun 12, 2015 11:48 pm
Re: Tetrad Development (Civic Auditorium)
Construction fence is up on the south side and they are working on installing it on the east side today. We were told that they were starting with demo on the north side next week using a large crane, but no signs of a crane yet. Just three excavators and couple skidloaders so far.
- Omaha_Gabe
- Human Relations
- Posts: 731
- Joined: Tue Mar 08, 2011 1:22 pm
- Location: Midtown Crossings
Re: Tetrad Development (Civic Auditorium)
as per Stotherts facebook:
The fence is going up around the Civic Auditorium. We expect demolition to begin on the north side of the building next week. On track to be completed by the end of this year.
The fence is going up around the Civic Auditorium. We expect demolition to begin on the north side of the building next week. On track to be completed by the end of this year.
Re: Tetrad Development (Civic Auditorium)
Wow, by the end of the year? They were saying 18 months for demo back in December 2015. I always thought that seemed too long. Maybe they were including the whole pre-bid / bid period too.Omaha_Gabe wrote:as per Stotherts facebook:
The fence is going up around the Civic Auditorium. We expect demolition to begin on the north side of the building next week. On track to be completed by the end of this year.
He said "They are some big, ugly red brick buildings"
...and then they were gone.
...and then they were gone.
- skinzfan23
- City Council
- Posts: 9218
- Joined: Mon Feb 09, 2004 11:26 am
- Location: Omaha/Bellevue
Re: Tetrad Development (Civic Auditorium)
I just hope that the land doesn't sit vacant or as a parking lot after demolition.
-
- Planning Board
- Posts: 2959
- Joined: Sun Mar 11, 2012 12:48 pm
- Location: Beyond Thunderdome
Re: Tetrad Development (Civic Auditorium)
skinzfan23 wrote:I just hope that the land doesn't sit vacant or as a parking lot after demolition.
You know that's exactly what is going to happen.
No posts exist for this topic
Re: Tetrad Development (Civic Auditorium)
I'm fully expecting just that.MadMartin8 wrote:skinzfan23 wrote:I just hope that the land doesn't sit vacant or as a parking lot after demolition.
You know that's exactly what is going to happen.
When fortune smiles on something as violent and ugly as revenge, it seems proof like no other that not only does God exist, you're doing his will.
The Bride
The Bride
-
- Home Owners Association
- Posts: 79
- Joined: Fri Jun 12, 2015 11:48 pm
Re: Tetrad Development (Civic Auditorium)
Updated schedule:
27June - Begin demo of Mancuso and Music Halls
22Aug - Begin demo of auditorium
2Oct - Slab and foundation removals
27June - Begin demo of Mancuso and Music Halls
22Aug - Begin demo of auditorium
2Oct - Slab and foundation removals
Re: Tetrad Development (Civic Auditorium)
When can I park on it?yellowcolumbia wrote:Updated schedule:
27June - Begin demo of Mancuso and Music Halls
22Aug - Begin demo of auditorium
2Oct - Slab and foundation removals
When fortune smiles on something as violent and ugly as revenge, it seems proof like no other that not only does God exist, you're doing his will.
The Bride
The Bride
-
- Home Owners Association
- Posts: 79
- Joined: Fri Jun 12, 2015 11:48 pm
Re: Tetrad Development (Civic Auditorium)
You can park in the garage now. My understanding is that everything else on the lot will be removed, then graded and seeded while we wait for the development RFP.RNcyanide wrote: When can I park on it?
Re: Tetrad Development (Civic Auditorium)
They already did the RFP, that was what Tetrad won.yellowcolumbia wrote:My understanding is that everything else on the lot will be removed, then graded and seeded while we wait for the development RFP.
Omaha Skyline Photos, Omaha Aerial Photos, and More.
Website: www.bradwilliamsphotography.com
Facebook: www.facebook.com/bradwilliamsphotography
Twitter: www.twitter.com/bradwphoto
Instagram: www.instagram.com/bradwilliamsphotography
YouTube: www.youtube.com/@bradwilliamsphoto
- Omaha Cowboy
- The Don
- Posts: 1013183
- Joined: Wed Jan 07, 2004 5:31 am
- Location: West Omaha
Re: Tetrad Development (Civic Auditorium)
At least it appears we have a schedule/timetable for the Demo completion.. It's been a long time coming..
This location should yield a significant, signature development (potentially a highrise) for downtown.. Keeping my fingers crossed...
Ciao..LiO...Peace
This location should yield a significant, signature development (potentially a highrise) for downtown.. Keeping my fingers crossed...
Ciao..LiO...Peace
Go Cowboys!
Re: Tetrad Development (Civic Auditorium)
I'm pretty sure this ones happening although since we are west of the mighty Mo it'll probably be cut in half with the other half going downtown DSM.
15-17, 26, 32
Re: Tetrad Development (Civic Auditorium)
One last aerial of the Civic before Demo...
Omaha Skyline Photos, Omaha Aerial Photos, and More.
Website: www.bradwilliamsphotography.com
Facebook: www.facebook.com/bradwilliamsphotography
Twitter: www.twitter.com/bradwphoto
Instagram: www.instagram.com/bradwilliamsphotography
YouTube: www.youtube.com/@bradwilliamsphoto
-
- Planning Board
- Posts: 2959
- Joined: Sun Mar 11, 2012 12:48 pm
- Location: Beyond Thunderdome
Re: Tetrad Development (Civic Auditorium)
Brad wrote:One last aerial of the Civic before Demo...
That's going to be one big parking lot for the next 5-10 years.
No posts exist for this topic
- skinzfan23
- City Council
- Posts: 9218
- Joined: Mon Feb 09, 2004 11:26 am
- Location: Omaha/Bellevue
Re: Tetrad Development (Civic Auditorium)
Another great photo!
Re: Tetrad Development (Civic Auditorium)
Thanks!
Omaha Skyline Photos, Omaha Aerial Photos, and More.
Website: www.bradwilliamsphotography.com
Facebook: www.facebook.com/bradwilliamsphotography
Twitter: www.twitter.com/bradwphoto
Instagram: www.instagram.com/bradwilliamsphotography
YouTube: www.youtube.com/@bradwilliamsphoto
- Omaha Cowboy
- The Don
- Posts: 1013183
- Joined: Wed Jan 07, 2004 5:31 am
- Location: West Omaha
Re: Tetrad Development (Civic Auditorium)
Absolutely fantastic pic Brad ...Brad wrote:One last aerial of the Civic before Demo...
Ciao..LiO...Peace
Go Cowboys!
Re: Tetrad Development (Civic Auditorium)
Thanks Lou!
Omaha Skyline Photos, Omaha Aerial Photos, and More.
Website: www.bradwilliamsphotography.com
Facebook: www.facebook.com/bradwilliamsphotography
Twitter: www.twitter.com/bradwphoto
Instagram: www.instagram.com/bradwilliamsphotography
YouTube: www.youtube.com/@bradwilliamsphoto
-
- Home Owners Association
- Posts: 79
- Joined: Fri Jun 12, 2015 11:48 pm
Re: Tetrad Development (Civic Auditorium)
Well, they have silt fence and other erosion control measures up, but not much else to see besides a few trees and bushes. The abatement contractor has still been there working most days.yellowcolumbia wrote:Updated schedule:
27June - Begin demo of Mancuso and Music Halls
22Aug - Begin demo of auditorium
2Oct - Slab and foundation removals
Re: Tetrad Development (Civic Auditorium)
There seems to be a lot of negativity as to whether any project will eventually be built here. Don't forget that one of the partners of this project is NuStyle Development. I have never known Todd to commit to a project and then walk away from it. How what gets constructed there resembles the original proposal remains to be seen. I would bet the 16 story office building does not happen, as there is simply not the demand for that kind of space downtown. But look at the original proposal for the Capitol District compared to what is actually being constructed. The hotel lost a few floors as has the apartment building. The underground parking is gone, and what was to be a second apartment building along I-480 is now an above ground parking garage. And I haven't seen one sign of any construction of the two smaller buildings fronting Capitol Ave. There will be construction on the Civic site. It just remains to be seen what kind of development occurs there in 2017 - 2020.
Always a business-oriented city hungry for growth and focused on development with laser intensity, Omaha aimed high, reached for momentum and found critical mass.
Re: Tetrad Development (Civic Auditorium)
Oh, and there has been a tiny bit of demo here. There was a smoke stack on the back of the building. It was knocked over a few weeks ago, and hauled away.
Always a business-oriented city hungry for growth and focused on development with laser intensity, Omaha aimed high, reached for momentum and found critical mass.
Re: Tetrad Development (Civic Auditorium)
I tend to agree - ConAgra pulling out opened up so much extra office space that the tower here simply isn't needed.OmahaChef wrote:There seems to be a lot of negativity as to whether any project will eventually be built here. Don't forget that one of the partners of this project is NuStyle Development. I have never known Todd to commit to a project and then walk away from it. How what gets constructed there resembles the original proposal remains to be seen. I would bet the 16 story office building does not happen, as there is simply not the demand for that kind of space downtown. But look at the original proposal for the Capitol District compared to what is actually being constructed. The hotel lost a few floors as has the apartment building. The underground parking is gone, and what was to be a second apartment building along I-480 is now an above ground parking garage. And I haven't seen one sign of any construction of the two smaller buildings fronting Capitol Ave. There will be construction on the Civic site. It just remains to be seen what kind of development occurs there in 2017 - 2020.
Regarding the two smaller buildings on Capitol, I guess I figured they wouldn't start messing with those until the hotel/apartment building were nearing completion.
- PotatoeEatsFish
- Human Relations
- Posts: 750
- Joined: Wed Jul 22, 2015 11:59 pm
Re: Tetrad Development (Civic Auditorium)
I forgot today was my one year anniversary of joining eomaha.
#SaveTheUglyGrainSilos2024
- nebugeater
- City Council
- Posts: 108953
- Joined: Wed Aug 04, 2004 6:07 pm
- Location: Gretna NE
Re: Tetrad Development (Civic Auditorium)
PotatoeEatsFish wrote:I forgot today was my one year anniversary of joining eomaha.
Where is the party!!!!
For the record NEBUGEATER does not equal BUGEATER !!!!!!!
Re: Tetrad Development (Civic Auditorium)
NEDodger wrote:I tend to agree - ConAgra pulling out opened up so much extra office space that the tower here simply isn't needed.OmahaChef wrote:There seems to be a lot of negativity as to whether any project will eventually be built here. Don't forget that one of the partners of this project is NuStyle Development. I have never known Todd to commit to a project and then walk away from it. How what gets constructed there resembles the original proposal remains to be seen. I would bet the 16 story office building does not happen, as there is simply not the demand for that kind of space downtown. But look at the original proposal for the Capitol District compared to what is actually being constructed. The hotel lost a few floors as has the apartment building. The underground parking is gone, and what was to be a second apartment building along I-480 is now an above ground parking garage. And I haven't seen one sign of any construction of the two smaller buildings fronting Capitol Ave. There will be construction on the Civic site. It just remains to be seen what kind of development occurs there in 2017 - 2020.
Regarding the two smaller buildings on Capitol, I guess I figured they wouldn't start messing with those until the hotel/apartment building were nearing completion.
You wonder with all the younger people wanting to live downtown, if it's going to take a generation for a serious increase of demand for downtown office space.
Re: Tetrad Development (Civic Auditorium)
Sounds logical, until you think about what kind of company would actually want to rent the type of space the vacated ConAgra buildings contain. There just aren't that many companies looking for that type of space any longer.....which is executive suite-style floor to ceiling individual offices comprising most of the building. Most companies are now looking for more open-office collaborative space. Extensive remodeling, if not a major gut-job would be required in most cases. It would be less hassle for a company to move into new space already configured for open plan office space. Now if they were to go ahead and pre-gut the buildings and prepare them for open office space before leasing, the buildings would have more of an effect on the market for such space.NEDodger wrote:I tend to agree - ConAgra pulling out opened up so much extra office space that the tower here simply isn't needed.OmahaChef wrote:There seems to be a lot of negativity as to whether any project will eventually be built here. Don't forget that one of the partners of this project is NuStyle Development. I have never known Todd to commit to a project and then walk away from it. How what gets constructed there resembles the original proposal remains to be seen. I would bet the 16 story office building does not happen, as there is simply not the demand for that kind of space downtown. But look at the original proposal for the Capitol District compared to what is actually being constructed. The hotel lost a few floors as has the apartment building. The underground parking is gone, and what was to be a second apartment building along I-480 is now an above ground parking garage. And I haven't seen one sign of any construction of the two smaller buildings fronting Capitol Ave. There will be construction on the Civic site. It just remains to be seen what kind of development occurs there in 2017 - 2020.
He said "They are some big, ugly red brick buildings"
...and then they were gone.
...and then they were gone.
-
- Home Owners Association
- Posts: 79
- Joined: Fri Jun 12, 2015 11:48 pm
Re: Tetrad Development (Civic Auditorium)
A bit of visible progress this morning.
Re: Tetrad Development (Civic Auditorium)
Sweet, thanks for the update!
Omaha Skyline Photos, Omaha Aerial Photos, and More.
Website: www.bradwilliamsphotography.com
Facebook: www.facebook.com/bradwilliamsphotography
Twitter: www.twitter.com/bradwphoto
Instagram: www.instagram.com/bradwilliamsphotography
YouTube: www.youtube.com/@bradwilliamsphoto
Re: Tetrad Development (Civic Auditorium)
Pretty sure that mist machine is for asbestos. Could be a slow demo if they have to worry about that the whole time.
Re: Tetrad Development (Civic Auditorium)
Its not usually followed very strictly, but technically any dust leaving your property is considered pollution, even if its "clean" dirt. That's why you see the big companies putting down water while they are grading.iamjacobm wrote:Pretty sure that mist machine is for asbestos. Could be a slow demo if they have to worry about that the whole time.
Omaha Skyline Photos, Omaha Aerial Photos, and More.
Website: www.bradwilliamsphotography.com
Facebook: www.facebook.com/bradwilliamsphotography
Twitter: www.twitter.com/bradwphoto
Instagram: www.instagram.com/bradwilliamsphotography
YouTube: www.youtube.com/@bradwilliamsphoto
Re: Tetrad Development (Civic Auditorium)
Anyone know what they are doing with all the facde brick? I'd like to obtain a few.
-
- Home Owners Association
- Posts: 79
- Joined: Fri Jun 12, 2015 11:48 pm
Re: Tetrad Development (Civic Auditorium)
The stuff they have taken down so far has been pulverized, becoming an operating surface for their excavators. Not sure if they will be more careful as they continue. I'll let you know if they start stockpiling it separately.mr. omaha wrote:Anyone know what they are doing with all the facde brick? I'd like to obtain a few.
I'm pretty sure the misting fan is just for dust control.
Starting on the north wall of the Mancuso Hall this morning.
- Attachments
-
- IMG_2850.JPG (113.86 KiB) Viewed 4908 times
Re: Tetrad Development (Civic Auditorium)
I know HDR is involved with planning a new high-rise, mixed-use tower as of recently, so I wonder if this is the intended site?
Socialism is a philosophy of failure, the creed of ignorance, and the gospel of envy, its inherent virtue is the equal sharing of misery. - Winston Churchill
-
- Planning Board
- Posts: 2746
- Joined: Wed Sep 08, 2004 3:00 pm
- Location: Metro Detroit Michigan
Re: Tetrad Development (Civic Auditorium)
What's the over/under on this thing looking anything like the proposal?
Re: Tetrad Development (Civic Auditorium)
I wouldn't hold my breath on any of these proposals/planned projects. I'm not even sure what HDR is planning given the availability of the ConAgra campus - but they're definitely working on something (I'm sure someone here knows)NovakOmaha wrote:What's the over/under on this thing looking anything like the proposal?
Socialism is a philosophy of failure, the creed of ignorance, and the gospel of envy, its inherent virtue is the equal sharing of misery. - Winston Churchill
- Omaha Cowboy
- The Don
- Posts: 1013183
- Joined: Wed Jan 07, 2004 5:31 am
- Location: West Omaha
Re: Tetrad Development (Civic Auditorium)
I think what the past has taught us, especially in lieu of the Wallstreet Tower fiasco from years back and more recently the crapfest that became HDR pulling the plug on downtown, is to NOT get full on PUFFY excited over anything "proposed"..S33 wrote:I wouldn't hold my breath on any of these proposals/planned projects. I'm not even sure what HDR is planning given the availability of the ConAgra campus - but they're definitely working on something (I'm sure someone here knows)NovakOmaha wrote:What's the over/under on this thing looking anything like the proposal?
Until I see earth move and ultimately a tower crane (or 2) in the air, I just note the "proposal" in my mind, hope it comes to fruition, and move along with zero expectation that it actually will become reality...