Construction Has Begun
1. Looking North West

2. Looking North East




First national tower is visible in pic 2....Stargazer wrote:I think the stadium will have a little better angle on the skyline than TD Ameritrade... don't you think? :)



Brad wrote:CONSTRUCTION: Sarpy County/Royals Stadium
1. Looking North West
Progress at the site of Sarpy County's planned 6,000-seat baseball stadium for the Omaha Royals has run afoul of Nebraska's harsh winter.
In early December, contractors stopped excavation work on the $26 million project west of Papillion. Snow and subzero temperatures dashed the county's ambitious plans to finish the grading, pour concrete and have the stadium seating bowl completed by Christmas.
Three major snowstorms, separated by bone-chilling cold, hit in just a few weeks. Snow drifted into mounds around dozens of pieces of construction equipment that sat idle along Nebraska Highway 370. Contractors, already working under a tight schedule, lost more than a month.
His firm's agreement calls for the stadium to be built by March 15, 2011, about a month before the start of the Royals' 2011 baseball season.
Despite the unusually harsh winter, architects, contractors, representatives of the minor league baseball club and county officials say the stadium will be done on time.
No contingency plans are being discussed. If contractors cannot meet their deadlines, no fallback plans exist for a Rosenblatt Stadium encore
In Sarpy County, Meradith hopes to have his ballpark's final design plans by late February. After that, the county and the public will have a better sense of the construction schedule.
Last week's relative warm-up allowed contractors to build a new access road connecting the 31-acre site to Nebraska Highway 370. Limited excavation and grading work has resumed.
Workers hope to pour the stadium's concrete footings around Jan. 25. The steel framing would go up next, perhaps in March.
http://www.sarpyballpark.com wrote:Foundation work is taking place this month, with concrete footings poured for the main seating area, outfield area and dugouts. The view in the photo below is from center field, looking toward the main seating area.

Jeffrey Robb WORLD-HERALD STAFF WRITER wrote:The Omaha Royals' new stadium in Sarpy County remains on schedule to host baseball in spring 2011.
In recent weeks, crews have been able to move dirt and place concrete footings for the $25 million stadium, Sarpy County Administrator Mark Wayne said Tuesday. One dugout has been poured.
Jeffrey Robb WORLD-HERALD STAFF WRITER wrote:Wayne said precast buildings were ordered last week and should be ready to install starting by June.
After those are delivered, Wayne said, the stadium structure should go up quickly. It has little steel compared with Omaha's new downtown stadium. The Sarpy stadium's seating, for instance, will be set into a bowl on the ground, not built up.
Jeffrey Robb WORLD-HERALD STAFF WRITER wrote:That's key, Wayne said, because the field is scheduled to be installed in June so the grass has the rest of the growing season to get established.

Precast? I thought I was just joking when I called it "porta-potty park"...Jeffrey Robb WORLD-HERALD STAFF WRITER wrote:Wayne said precast buildings were ordered last week and should be ready to install starting by June.
After those are delivered, Wayne said, the stadium structure should go up quickly. It has little steel compared with Omaha's new downtown stadium. The Sarpy stadium's seating, for instance, will be set into a bowl on the ground, not built up.
There is also a lot of precast in the new downtown stadium and all of the exterior walls at Midtown Crossing are precast. Heck the last 2 parking garages I have seen in Omaha have been all precast.Greg S wrote:Precast was used to speed up the construction of our very own Qwest Center Omaha....
Greg

HskrFanMike wrote:Maybe I misinterpreted what "precast buildings" meant. I know that precast panels are frequently used in construction (and TD Ameritrade Park is using precast for the seating), but I took "precast buildings" meant the entire building was precast.
I am sure it will look fine. The new HyVee's are all precast.HskrFanMike wrote:No, but the press box, concession stands, dugouts/locker rooms, and restrooms are all covered.

Bingo.StreetsOfOmaha wrote:I don't mind the use of prefab either. I think it's a very economical way to build.
However, it annoys me that in the 21st century, they haven't developed the technology to make the precast brick panels seamless... I hate that you can see the outline of the panels. This really bothers me on buildings like those of Midtown Crossing.
They do have seamless precast walls of all types. However, I think they are much more expensive and tougher to work with.StreetsOfOmaha wrote:I don't mind the use of prefab either. I think it's a very economical way to build.
However, it annoys me that in the 21st century, they haven't developed the technology to make the precast brick panels seamless... I hate that you can see the outline of the panels. This really bothers me on buildings like those of Midtown Crossing.
Just for comparison, it takes 11 minutes to go from I-680 and Dodge to Rosenblatt. Just sayin'...Greg S wrote:Went by the site yesterday. Took me all of 12 minutes to go from there to I-680 and Dodge.
Greg
It won't once congestion from future sprawl out there really picks up.Greg S wrote:Went by the site yesterday. Took me all of 12 minutes to go from there to I-680 and Dodge.
Greg
There you go... same commute to Sarpy... and a better minor league baseball venue to boot.11 minutes to go from I-680 and Dodge to Rosenblatt. Just sayin'...

Maybe the same for you west o people. Hardly the same for east Omaha or CB.Stargazer wrote:There you go... same commute to Sarpy... and a better minor league baseball venue to boot.11 minutes to go from I-680 and Dodge to Rosenblatt. Just sayin'...![]()
Is that cost out there yet? I'd love to consider it, although probably wouldn't be feasible for a few years when the little ones are more likely to sit for at least part of a game!joeglow wrote:Anyway, nice picture Stargazer and thanks for the update. The wife and I are looking at the cost of season tickets once this is up and running.
That is our biggest challenge right now. With our boys being 1, 4 & 7, it may be a couple years. However, we talked about getting 2 sets so we can mix it up with the kids and go to some games with just us.cdub wrote:Is that cost out there yet? I'd love to consider it, although probably wouldn't be feasible for a few years when the little ones are more likely to sit for at least part of a game!joeglow wrote:Anyway, nice picture Stargazer and thanks for the update. The wife and I are looking at the cost of season tickets once this is up and running.
It's on the ORoyals web site; look for their ticket guide (it may mention group tickets). Season tickets start at around $561 IIRC going upwards.cdub wrote:Is that cost out there yet? I'd love to consider it, although probably wouldn't be feasible for a few years when the little ones are more likely to sit for at least part of a game!joeglow wrote:Anyway, nice picture Stargazer and thanks for the update. The wife and I are looking at the cost of season tickets once this is up and running.
windsor wrote:One would assume this is looking at home plat?