Q Street: 192nd - 204th

Trains, Planes, and Automobiles (and Streetcars!).
riceweb
Human Relations
Posts: 617
Joined: Thu Mar 22, 2007 12:54 am
Location: Omaha, NE

Q Street: 192nd - 204th

Post by riceweb »

Saw a sign on Q Street near 204th St that said there's an upcoming information session about a new project. I'm assuming Q Street will be widened all the way to 204th?
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Street Widening

Post by BRoss »

riceweb wrote: Mon May 13, 2024 9:15 am Saw a sign on Q Street near 204th St that said there's an upcoming information session about a new project. I'm assuming Q Street will be widened all the way to 204th?
Probably 204th & F. They have plans to widen the intersection for turn lanes on F Street this year.
riceweb
Human Relations
Posts: 617
Joined: Thu Mar 22, 2007 12:54 am
Location: Omaha, NE

Re: Street Widening

Post by riceweb »

Seems like there are two projects, one on 204th at F, and another on Q itself, since the city has labeled it on the sign as "Q STREET PROJECT". But I haven't found any info online about it.
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Street Widening

Post by BRoss »

riceweb wrote: Mon May 13, 2024 11:47 am Seems like there are two projects, one on 204th at F, and another on Q itself, since the city has labeled it on the sign as "Q STREET PROJECT". But I haven't found any info online about it.
Oh, it might be the bridge replacement on the Elkhorn River. The TIP has it in FY 2027.

I've seen them list 192nd to 204th in the past TIPs and CIPs with a TBD year but it dropped off a while ago. So I don't think there's anything coming for that any time soon.
cchandler790
New to the Neighborhood
Posts: 36
Joined: Mon Feb 11, 2019 2:40 pm

Re: Street Widening

Post by cchandler790 »

[/img]
riceweb wrote: Mon May 13, 2024 11:47 am Seems like there are two projects, one on 204th at F, and another on Q itself, since the city has labeled it on the sign as "Q STREET PROJECT". But I haven't found any info online about it.
Yes! In 2025 Q st will be widened from 192nd to 204th St.

Image

Image
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Street Widening

Post by BRoss »

cchandler790 wrote: Mon May 13, 2024 10:44 pm [/img]
riceweb wrote: Mon May 13, 2024 11:47 am Seems like there are two projects, one on 204th at F, and another on Q itself, since the city has labeled it on the sign as "Q STREET PROJECT". But I haven't found any info online about it.
Yes! In 2025 Q st will be widened from 192nd to 204th St.

Image

Image
Maybe it was the Douglas County Highway Plan that I used to see this project, which is why I haven't been seeing it in the TIP and CIP. :)

Notice a little further down is has Construction Period UNK. Normally it will list a year when construction is tentatively set to happen. I've always viewed these pages without a construction year listed as more speculative. I would love to be wrong though. Hopefully something will get posted online in the next few days.

Image

https://www.dcengineer.org/images/stori ... x_2024.pdf
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Street Widening

Post by BRoss »

cchandler790 wrote: Mon May 13, 2024 10:44 pm
riceweb wrote: Mon May 13, 2024 11:47 am Seems like there are two projects, one on 204th at F, and another on Q itself, since the city has labeled it on the sign as "Q STREET PROJECT". But I haven't found any info online about it.
Yes! In 2025 Q st will be widened from 192nd to 204th St.
Looks like you were right. I'm surprised they still listed the construction year as unknown in this fiscal year's plan, but Keep Omaha Moving now finally has the project listed:

https://keepomahamoving.com/projects/q- ... ct-c-28478

Public hearing is tomorrow night:
May 21, 2024
5pm to 7pm, brief presentation at 5:30pm
Millard Horizon High School
5300 George B. Lake Parkway
Omaha, NE 68022
Construction will be 2025-2026.
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Street Widening

Post by BRoss »

Handout for the Q Street widening project: https://www.dcengineer.org/images/C-284 ... out-v4.pdf
cchandler790
New to the Neighborhood
Posts: 36
Joined: Mon Feb 11, 2019 2:40 pm

Re: Street Widening

Post by cchandler790 »

It's a very needed project! Glad it's getting done, with all the new developments. I wish 204th or highway 6 was an expressway.
CompSci99
New to the Neighborhood
Posts: 35
Joined: Thu Aug 17, 2023 12:09 am

Re: Street Widening

Post by CompSci99 »

cchandler790 wrote: Tue May 21, 2024 9:41 pm It's a very needed project! Glad it's getting done, with all the new developments. I wish 204th or highway 6 was an expressway.
I agree. I have no experience in transportation, but I feel like it was a huge missed opportunity to not make 204th into an expressway similar to west dodge. Just add in an interchange with west dodge road to the north, and curve to the west or east around gretna for another interchange with i-80. Would have helped with traffic on 204th through gretna and essentially served as a west o beltway, but now homes and businesses are built up to 204th and there are tons of signalized intersections being put up.
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

Presentation that has more info: https://keepomahamoving.com/application ... ebsite.pdf

Project will begin next year and last two construction seasons. Q Street will be closed during this time. OPPD will be replacing the large transmission poles beginning this fall.

No noise walls will be constructed along any of the project. An additional signal will go in at 201st Street. The only work being done on 204th is shorting the median noses; dual left turns will not be constructed there at this time (Q Street will be constructed with dual lefts, but initially only be striped for single).
Trips1
Home Owners Association
Posts: 133
Joined: Thu Jan 13, 2022 11:21 am

Re: Street Widening

Post by Trips1 »

cchandler790 wrote: Tue May 21, 2024 9:41 pm It's a very needed project! Glad it's getting done, with all the new developments. I wish 204th or highway 6 was an expressway.
I never seem learn and follow Waze and Google Maps to take 192nd North. If the Center Street intersection is not backed up, it is 3-4 minutes quicker than taking 204th. That is going from 192nd and Giles to Menards off 204th and Dodge.
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

The draft 2025 Douglas County Six-Year Highway Improvement Plan came out recently. This project has been moved from FY 2025 to 2026.
Nosebot
Home Owners Association
Posts: 105
Joined: Tue May 02, 2023 1:53 pm

Re: Q Street: 192nd - 204th

Post by Nosebot »

BRoss wrote: Thu Aug 22, 2024 9:32 pm This project has been moved from FY 2025 to 2026.
I'd assume this is due to all the housing construction going on the north and south side of Q?
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

Nosebot wrote: Thu Aug 22, 2024 10:14 pm
BRoss wrote: Thu Aug 22, 2024 9:32 pm This project has been moved from FY 2025 to 2026.
I'd assume this is due to all the housing construction going on the north and south side of Q?
No idea. I assume changing budget priorities. Road construction projects constantly get delayed. It can be frustrating.
User avatar
Brad
Photographer
Posts: 1036522
Joined: Sat Feb 28, 2004 6:03 pm
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by Brad »

BRoss wrote: Thu Aug 22, 2024 10:25 pm
Nosebot wrote: Thu Aug 22, 2024 10:14 pm
BRoss wrote: Thu Aug 22, 2024 9:32 pm This project has been moved from FY 2025 to 2026.
I'd assume this is due to all the housing construction going on the north and south side of Q?
No idea. I assume changing budget priorities. Road construction projects constantly get delayed. It can be frustrating.
I think they also do traffic counts and if its not growing as fast as they were thinking, they may change priorities a little.
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

Looks like this project starts Monday.

https://www.dcengineer.org/images/2025. ... __Q_st.pdf
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

Posting this here as well since it's related to this project:
BRoss wrote: Fri Oct 24, 2025 10:00 pm
Brad wrote: Fri Oct 24, 2025 1:32 pm We did one project it took OPPD way longer than expected to move the power poles back away from the new road.
Speaking of this, Q Street between 192nd & 204th appears to be way behind schedule for this same reason - or perhaps other utilities. I've been wondering since early this summer if they needed to move some of the wooden poles for this. The larger transmission lines were done last year, but these were still left as is.

From looking at the webcams, they have also seemed to have had a lot of weather delays due to frequent rain making things soggy, sometimes for many days at a time due to pooling. While we haven't had a crazy amount of rain (we are still technically under average this year), it has been frequent enough to where things haven't really been able to dry out enough for long periods this year. And not having the right conditions will certainly delay things.

But either way, these poles still have not been addressed and it's clear now that they need to move before they can continue paving the north side as well as continuing east (there's single pole on the south side in the way). And with where we are in the year, that window is quickly coming to a close.

I'm guessing this will drag into the middle of next year at the earliest, although I hope I'm wrong.
riceweb
Human Relations
Posts: 617
Joined: Thu Mar 22, 2007 12:54 am
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by riceweb »

They had originally said Fall 2025, but they did a quiet update on the projects page to say late Spring 2026. It's wild how far off course this project is though.

However, I am hopeful that they can open two lanes relatively soon, since it looks like they could have 2 lanes relatively quickly? It's not too far between segments if they could just hurry up and partially complete that stretch?
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

Pouring on the east side today. Looks like the pole that has been blocking it has been moved. So maybe they'll open two lanes over winter.
Q Street west of 192nd Pour.JPG
You do not have the required permissions to view the files attached to this post.
riceweb
Human Relations
Posts: 617
Joined: Thu Mar 22, 2007 12:54 am
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by riceweb »

Looks like eastbound lanes might be fully paved now? Even just for business access through that area, seems like they'll want to open up those lanes ASAP while they continue work on the westbound lanes?
riceweb
Human Relations
Posts: 617
Joined: Thu Mar 22, 2007 12:54 am
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by riceweb »

OPPD did finally move the power lines so construction has continued with some more leveling ahead of paving.
djc311
Planning Board
Posts: 2128
Joined: Tue Mar 09, 2004 10:44 pm
Location: Omaha

Re: Q Street: 192nd - 204th

Post by djc311 »

riceweb wrote: Thu Mar 05, 2026 8:40 am OPPD did finally move the power lines so construction has continued with some more leveling ahead of paving.
Good to see some progress... I'm sure the businesses going in at 204th & Q are anxiously awaiting the completion.

FWIW, I don't think a single tenant has signed on for the two new retail buildings at the corner of 192nd & Q St. I imagine part of that is due to the construction mess... other part is probably ridiculously high rent rates for that location.
riceweb
Human Relations
Posts: 617
Joined: Thu Mar 22, 2007 12:54 am
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by riceweb »

And I looked a little closer at the cameras for this project, and it looks like they might still be doing some work to bury the lines, but the overhead ones are at least gone
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

riceweb wrote: Thu Mar 05, 2026 8:40 am OPPD did finally move the power lines so construction has continued with some more leveling ahead of paving.
Yeah they finally removed the ones on the north side about 3 weeks ago. I periodically check the web cams and was surprised to finally see them gone one day.

They finally started grading where they were over the last couple days. There hadn't been much movement since the last snow.
locoluke
Home Owners Association
Posts: 185
Joined: Sun Mar 30, 2025 11:16 pm

Re: Q Street: 192nd - 204th

Post by locoluke »

I drove by the other day on 204th. They’ve installed new, slightly larger signal poles at 204th and Q. It also looked like the paving of the eastbound lanes from 204th to 192nd may have been complete.
Ride a bike
:hammer:
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

locoluke wrote: Thu Mar 05, 2026 10:53 am It also looked like the paving of the eastbound lanes from 204th to 192nd may have been complete.
The eastbound lanes were completed last fall. They've been waiting on OPPD to move the power poles on the north side so they could start the westbound lanes.
User avatar
nebugeater
City Council
Posts: 110917
Joined: Wed Aug 04, 2004 6:07 pm
Location: Gretna NE

Re: Q Street: 192nd - 204th

Post by nebugeater »

Any chance this is completed before 2027? :;):
For the record  NEBUGEATER does not equal BUGEATER    !!!!!!!
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

nebugeater wrote: Sat Mar 07, 2026 8:11 am Any chance this is completed before 2027? :;):
It was originally supposed to be done by the end of last year. Hopefully it will be done by this summer. I think the paving of the westbound lanes will go pretty quickly once they finish grading.
riceweb
Human Relations
Posts: 617
Joined: Thu Mar 22, 2007 12:54 am
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by riceweb »

Facebook tells me this is now projected for August. Absolutely ridiculous how this timeline has shifted out for a very straightforward project.

Is Harrison going to be ripped up now soon?
djc311
Planning Board
Posts: 2128
Joined: Tue Mar 09, 2004 10:44 pm
Location: Omaha

Re: Q Street: 192nd - 204th

Post by djc311 »

riceweb wrote: Mon Mar 30, 2026 4:07 pm Facebook tells me this is now projected for August. Absolutely ridiculous how this timeline has shifted out for a very straightforward project.

Is Harrison going to be ripped up now soon?
I was wondering the same thing because they have yard signs with QR codes on them mentioning a road construction project will begin soon. I haven't been able to scan the code when I'm driving by.

There's one sign about 2-3 blocks south of Harrison on 180th. I've also seen them on Harrison. Harrison should be 4 lanes all the way out to 204th, IMO.

Whatever they're going to tear up, I need to plan to avoid.
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

riceweb wrote: Mon Mar 30, 2026 4:07 pm Facebook tells me this is now projected for August. Absolutely ridiculous how this timeline has shifted out for a very straightforward project.

Is Harrison going to be ripped up now soon?
I would hope it doesn't take until August. The grading for the westbound lanes looks pretty close to where they just need to pour the cement. And the traffic signals have started to go up too.

For Harrison, are they talking 216th? It was supposed to start last August but looking at the webcam, it hasn't started yet. As for the rest of Harrison, MAPA is looking at that along with 168th:
MAPA 2026 TIP wrote: 2025-004 168th Street & Harrison Street Corridors Improvements

The project will design the 168th Street corridor from approximately V to Harrison Street and Harrison Street from 157th Street to 204th Street using the City’s Complete Streets process to identify the community’s needs, context of the area, and identify safety issues that need to be addressed. We anticipate that this will include widening of 168th Street and Harrison Street as well as providing sidewalk and/or trail access to provide connectivity, as appropriate. This project will coordinate closely with Sarpy County’s 168th St. Hwy 370 - Harrison St. project and the City’s 168th Street project from Q to Center, which is currently being constructed. This project will further determine overall project cost needs for construction and help to write an application to apply for federal funds for a shovel-ready project.

The project will include 168th Street from V Street to Harrison Street as well as Harrison Street from 156th to 204th Streets. The project will be closely coordinated with Sarpy County’s current 168th St. Hwy 370 - Harrison St. project currently funded through MAPA.
User avatar
Brad
Photographer
Posts: 1036522
Joined: Sat Feb 28, 2004 6:03 pm
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by Brad »

BRoss wrote: Tue Mar 31, 2026 9:31 am For Harrison, are they talking 216th? It was supposed to start last August but looking at the webcam, it hasn't started yet.
That webcam of Harrison & 216 is in a weird spot, quite a bit west near 222nd street. Here is an aerial I took on November 3. 2025, showing the progress at 216 & Harrison.

20251103881A8180.jpg
You do not have the required permissions to view the files attached to this post.
User avatar
nebugeater
City Council
Posts: 110917
Joined: Wed Aug 04, 2004 6:07 pm
Location: Gretna NE

Re: Q Street: 192nd - 204th

Post by nebugeater »

Brad wrote: Tue Mar 31, 2026 12:46 pm
BRoss wrote: Tue Mar 31, 2026 9:31 am For Harrison, are they talking 216th? It was supposed to start last August but looking at the webcam, it hasn't started yet.
That webcam of Harrison & 216 is in a weird spot, quite a bit west near 222nd street. Here is an aerial I took on November 3. 2026, showing the progress at 216 & Harrison.


20251103881A8180.jpg
Can I see some more photos from November 6, 2026? IF the right ones are there, I might plan a trip to Vegas.
For the record  NEBUGEATER does not equal BUGEATER    !!!!!!!
User avatar
Brad
Photographer
Posts: 1036522
Joined: Sat Feb 28, 2004 6:03 pm
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by Brad »

LOL.... 2025
User avatar
nebugeater
City Council
Posts: 110917
Joined: Wed Aug 04, 2004 6:07 pm
Location: Gretna NE

Re: Q Street: 192nd - 204th

Post by nebugeater »

Brad wrote: Tue Mar 31, 2026 1:00 pmLOL.... 2025
Dang.... that is what I figured but had to check!
For the record  NEBUGEATER does not equal BUGEATER    !!!!!!!
User avatar
Brad
Photographer
Posts: 1036522
Joined: Sat Feb 28, 2004 6:03 pm
Location: Omaha, NE

Re: Q Street: 192nd - 204th

Post by Brad »

Brad wrote: Tue Mar 31, 2026 12:46 pm
BRoss wrote: Tue Mar 31, 2026 9:31 am For Harrison, are they talking 216th? It was supposed to start last August but looking at the webcam, it hasn't started yet.
That webcam of Harrison & 216 is in a weird spot, quite a bit west near 222nd street. Here is an aerial I took on November 3. 2025, showing the progress at 216 & Harrison.


20251103881A8180.jpg
Apparently the Harrison Street portion may open later this week or early next week. Still some paving to complete on 216th Street.
User avatar
BRoss
IT Director
Posts: 10003363
Joined: Fri Aug 04, 2006 7:39 pm
Location: West Central Omaha

Re: Q Street: 192nd - 204th

Post by BRoss »

riceweb wrote: Mon Mar 30, 2026 4:07 pm Facebook tells me this is now projected for August. Absolutely ridiculous how this timeline has shifted out for a very straightforward project.
It's now been pushed out to September. It is honestly crazy this stretch has seen such big delays.
Douglas County Engineer wrote:The anticipated completion date for our Q Street closure from 192nd Street to 204th Street has been revised to September 2026, reflecting the time required for utility relocations.
https://www.dcengineer.org/images/2026. ... 4th_St.pdf
djc311
Planning Board
Posts: 2128
Joined: Tue Mar 09, 2004 10:44 pm
Location: Omaha

Re: Q Street: 192nd - 204th

Post by djc311 »

It’s ridiculous… it’s a mile and they’ve had the entire street closed the whole time, unlike many widening proejcts like 168th where they keep one lane open in each direction.

They said it’s due to utilities. It’s not rocket science, they knew where the utilities were before they started.