Widening of I-80 stretch should be done by November

http://www.omaha.com/index.php?u_pg=163 ... rnd=669197
The widening project is ahead of schedule. Hawkins Construction Co. has completed 70 percent of the work and used up 65 percent of the time allotted.
papiostud
Home Owners Association
Posts: 176
Joined: Sat Jul 10, 2004 12:33 am

Widening of I-80 stretch should be done by November

Post by papiostud »

Does anyone know if there is gonna be a median there like they do in Omaha? Or will cars still be able to cross over to the otherside and cause head on collissions.
User avatar
Brad
Photographer
Posts: 1036693
Joined: Sun Feb 29, 2004 12:03 am
Location: Omaha, NE

Widening of I-80 stretch should be done by November

Post by Brad »

I think there will be a cement barrier like in omaha all the way to lincoln.
User avatar
nebugeater
City Council
Posts: 111039
Joined: Wed Aug 04, 2004 11:07 pm
Location: Gretna NE

Widening of I-80 stretch should be done by November

Post by nebugeater »

From the looks of it driving it every day my GUESS would be that the concrete center will extend a little further out from where it now ends. About a 1/2 to 3/4 of a mile out the center line of the new E bound and the grading for the W bound seem to widden. At that point I would be really supprised if it continued. The grading seems to indicate a grass median with drainage.
papiostud
Home Owners Association
Posts: 176
Joined: Sat Jul 10, 2004 12:33 am

Widening of I-80 stretch should be done by November

Post by papiostud »

Yeah I see an area for grass in the middle now. I don't get that but okay. Maybe room for light rail? ha
CountOfMC
Library Board
Posts: 353
Joined: Tue Aug 17, 2004 2:24 am
Location: Downtown Milwaukee, Omaha

Widening of I-80 stretch should be done by November

Post by CountOfMC »

Has anyone driven the stretch of I-80 from Gretna to the 370 exit? While they're paving the WB lanes, it appears like there are/will be 4 lanes on the EB sides of the underpasses... how will they re-work this? I thought it was only going to be 3 lanes each way.
God created alcohol to keep the Irish from taking over the world!
User avatar
Brad
Photographer
Posts: 1036693
Joined: Sun Feb 29, 2004 12:03 am
Location: Omaha, NE

Widening of I-80 stretch should be done by November

Post by Brad »

I would guess that on of the lanes currently used will become the shoulder.
MTO
City Council
Posts: 7783
Joined: Wed Mar 09, 2005 5:49 pm
Location: Dundee

Widening of I-80 stretch should be done by November

Post by MTO »

Yes eventually there will be a large grass median starting somewhere in this project. I don’t know if it will be in this phase or not. Just check out the NDR’s website it does show plans for a wide 76’-88’ median.

http://www.nebraskatransportation.org/p ... 8phase.pdf
15-17, 26, 32